Taking out a chimney breast can free up useful floor space in a living room, kitchen or bedroom, and it is a common part of opening up an older house. But the brickwork you can see is only part of the chimney. The stack above, sometimes shared with next door, still has to be held up, which is why chimney breast removal is structural work rather than a simple knock-out.
This guide explains how chimney breasts are supported once removed, the approvals usually involved, what drives the cost and how to keep the mess under control. Cost figures are typical UK guide ranges only. FirstR8 Builds carries out structural changes and offers a free, no-obligation initial site consultation.

In short
If you remove a chimney breast but keep the stack, whatever is left above must be supported, normally on a steel beam designed by a structural engineer. Building control approval is required, and a party wall notice is often needed where the chimney sits on a shared wall. Removing the whole chimney from ground to roof avoids the support issue but costs more and involves roof work.
Breast, stack and flue: understanding the parts
The chimney breast is the projecting section of brickwork inside a room. Above it, the flues continue up through the upstairs rooms and loft, and the stack is the part that pokes out above the roof. In terraced and semi-detached houses, chimneys are often built back to back with the neighbour's on the party wall.
You can remove the breast from one room, from the ground and first floor, or the whole chimney including the stack. The more you take out at the bottom while keeping what is above, the more important the support design becomes.
How the remaining chimney is supported
There are two usual approaches, and the right one depends on the structure and what building control will accept.
- Steel beam: one or more steel beams, sometimes with padstones, built into the walls to carry the remaining masonry. This is the most common solution and is designed by a structural engineer with calculations.
- Gallows brackets: steel brackets fixed to the party wall to carry the remaining breast. They were widely used in the past and may still be accepted in some cases, but many building control bodies now expect an engineered design and some do not accept brackets.
Building control and the Party Wall Act
Removing all or part of a chimney breast is structural work and needs Building Regulations approval. Building control will usually want structural calculations, an inspection of the support before it is covered and checks that any flue serving a neighbour or remaining fireplace is unaffected.
If the chimney is on a party wall, the Party Wall Act will often apply, because the work involves cutting into the shared wall to insert the support. That means serving notice on your neighbour in good time. See our Party Wall Act guide for how notices and surveyors work.
Planning permission is not usually needed for internal removal, but taking down a visible stack may need consent in a conservation area or on a listed building.
What chimney breast removal costs
As typical UK guide figures, removing a single ground-floor chimney breast with a steel beam often falls somewhere around £1,500 to £3,500, while taking out breasts on two floors, or the full chimney including the stack and roof repairs, can range from roughly £3,000 to £8,000 or more. These are broad ranges, not quotes.
The price depends on how many floors are involved, the support method, whether the stack is kept, the need for scaffolding and roof work, how the rubble is removed, making good to floors, walls and ceilings, and any extra work such as moving radiators or sockets. Engineer's fees, building control fees and party wall surveyor costs, if needed, are usually extra.
How the work is done
A single breast removal often takes a few days of work on site, though plastering and drying time follow. Expect noise and dust despite precautions, and plan to keep children and pets away from the area.
- Survey and structural design, building control application and party wall notices where needed.
- Rooms are cleared and sealed with dust sheets and screens; floors are protected.
- Temporary support is installed, then the masonry is cut out from the top of the removal zone down, a section at a time.
- The steel beam or approved support is installed, packed and inspected.
- Rubble is bagged and removed, then the floor, walls and ceiling are made good ready for plastering and decorating.
Things to check before you start
- Whether the chimney serves a working fireplace, boiler flue or the neighbour's flue.
- Whether removing the breast actually gains enough usable space to justify the cost. Measure the alcoves first.
- If you are selling soon, buyers' surveyors will look for building control sign-off for previous removals.
- If an earlier owner removed a breast without support, get it inspected. Unsupported masonry above is a genuine safety risk.
Mistakes to avoid
- Relying on old brackets without checking building control will accept them.
- Forgetting the party wall notice and having to stop work.
- Removing the breast on the ground floor and leaving the first floor breast without support designed for it.
- Not capping and ventilating a disused flue, which can lead to damp.
Frequently asked questions
- Do I need building regulations to remove a chimney breast?
- Yes. It is structural work, so it needs Building Regulations approval, usually with structural calculations and an inspection of the support.
- Can I use gallows brackets instead of a steel beam?
- Sometimes, but many building control bodies now expect an engineered steel support and some do not accept brackets. Agree the method before work starts.
- Do I need a party wall agreement to remove a chimney breast?
- Often yes, if the chimney is on a wall shared with a neighbour, because the support usually involves cutting into the party wall.
- How long does chimney breast removal take?
- A single breast is often a few days on site, plus time for plastering and drying. Full removal including the stack takes longer.
- Is it cheaper to remove the whole chimney?
- Not usually. Removing the full chimney avoids supporting the stack but involves roof work and scaffolding, so it often costs more.