An extension is usually the biggest building job a homeowner takes on, and the first question is always the same: what will it cost? The honest answer is that it depends on far more than the size of the room. This guide explains where the money goes, what changes the price, the planning rules you need to know about, how long the work usually takes and the questions worth asking any builder before you sign anything.
Every figure on this page is a rough guide to help you plan, not a quote. The only way to get a real number for your home is a site visit and a priced specification.

Rough cost ranges (a guide, not a quote)
Builders across the South East commonly talk about extension costs per square metre of floor area. As a very rough starting point, a straightforward single-storey extension built to a standard specification often lands somewhere in the region of £2,000 to £3,000 per square metre for the build itself. Higher specifications, difficult sites, large areas of glazing or complicated roofs can take it well beyond that.
That per-metre figure normally does not include VAT, architect or designer fees, structural engineer fees, planning and building control charges, the kitchen or bathroom you put inside, flooring, or decoration. Those items can add a significant amount on top, so it is sensible to budget for them separately from day one and keep a contingency of around 10 to 15 percent for things that only show up once the ground is opened.
Two-storey extensions usually cost more in total but can work out better value per square metre, because the foundations and roof are shared between two floors of new space.
What changes the price
Two extensions of the same size can have very different prices. The main factors are:
- Ground conditions and foundations: clay soil, nearby trees, drains running under the footprint or a high water table can mean deeper or specialist foundations.
- Roof type: a simple flat roof is generally cheaper than a pitched roof with tiles to match your house, and roof lanterns or rooflights add cost.
- Glazing: large bi-fold or sliding doors are one of the biggest single line items in many extensions.
- Structural work: opening up the back wall of the house to join the old and new space needs steel beams, padstones and temporary propping.
- Access: a narrow side passage or a terraced house with no rear access makes moving materials and waste slower.
- Kitchens and bathrooms: wet rooms and kitchens bring plumbing, extraction and electrical work that a plain living room does not.
- Finish level: flooring, underfloor heating, joinery and lighting choices can move the final figure considerably.
Planning permission or permitted development?
Many single-storey rear extensions can be built under permitted development rights, which means you do not need a full planning application, provided the extension stays within set limits on depth, height and materials. Limits differ between detached and other houses, and there is a prior approval route for larger rear extensions where neighbours are consulted.
Permitted development rights do not apply everywhere. Flats and maisonettes do not have them, and they can be restricted in conservation areas, for listed buildings, or where the council has removed them on a particular estate. Parts of Chichester, Arundel and the older streets of the coastal towns include conservation areas, so check with your local council (Arun, Chichester or Worthing) before assuming you are covered.
If you are relying on permitted development, a Lawful Development Certificate from the council is worth considering. It is not compulsory, but it gives you written proof that the extension was lawful, which helps when you sell.
Planning and building regulations are separate. Even if you do not need planning permission, almost every extension needs building regulations approval, covering foundations, structure, insulation, drainage, ventilation and fire safety.
How long does an extension take?
There are two timelines: the paperwork and the build. Design, drawings, structural calculations and any planning decision commonly take a few months before anyone breaks ground. A householder planning application normally has an eight-week determination period once it is validated.
On site, a typical single-storey rear extension often takes somewhere around three to four months from groundworks to handover, and two-storey work longer. Weather, material lead times (especially windows and doors) and changes made mid-build are the most common causes of delay.
The rough order of works is: setting out and foundations, drainage, walls up to roof level, roof structure and covering, windows and doors to make it watertight, first fix carpentry, plumbing and electrics, plastering, second fix and finishes, and finally knocking through into the existing house once the new space is sealed.
What to ask a builder before you sign
A good builder will be happy to answer these clearly:
- Is the quote itemised, and exactly what is excluded?
- Who will be on site day to day, and who manages the trades?
- How do you handle building control inspections?
- What is the payment schedule? Stage payments tied to completed work are normal; large up-front payments are a warning sign.
- How are changes priced if we alter the plan part-way through?
- Can we see photos of similar work you have done?
- What insurance do you hold, and will you put the agreement in writing?
Frequently asked questions
- Do I need an architect for a single-storey extension?
- You need proper drawings for building control and, if required, planning. These can come from an architect or an architectural technician. We work with experienced local architects and can point you in the right direction.
- Will I need to move out during an extension?
- Usually not. Most of the work happens outside the existing house, and the back wall is normally only opened once the new space is weatherproof. Expect a few disruptive weeks near the end.
- Is a per square metre price a reliable way to budget?
- It is useful for a first sense check only. Glazing, structure, ground conditions and the fit-out inside can all move the final price a long way, so get an itemised quote.