Kitchen installation: what to expect, step by step

A new kitchen is one of the most used and most noticed parts of any home, and fitting it well takes several trades working in the right order. Whether you are buying from a big retailer, an independent showroom or having units made, it helps to understand how the installation works before the old kitchen comes out.

This guide explains the stages, how long they take, who handles each part and the problems that most often catch homeowners out.

Kitchen installation completed by FirstR8 Builds in West Sussex

Before installation: planning and measuring

Most problems in a kitchen fit start at the design stage. The plan should be based on an accurate site survey, not just room dimensions, taking into account where the water supply, waste, gas and electrics are, where windows and radiators sit, and whether walls and floors are straight.

Moving a sink or hob to the other side of the room is possible but means new pipe runs, waste falls and possibly new circuits, so it costs more than keeping things where they are. Decide early so the trades can price it properly.

The installation process

A typical full kitchen replacement goes roughly like this:

  • Strip out the old kitchen and make safe the water, gas and electrics.
  • Any structural or layout work, such as removing a wall or moving a doorway.
  • First fix plumbing and electrics: new pipework, waste, cables, sockets positions and lighting runs.
  • Plastering and making good the walls and ceiling, then drying time.
  • Flooring, if it is going under the units, which many fitters prefer.
  • Fitting the base and wall units, levelling and fixing them securely.
  • Templating and fitting worktops. Stone and quartz worktops are usually templated once the units are in and fitted a week or two later.
  • Second fix: sink, taps, appliances, hob, extractor, sockets and lighting.
  • Tiling or splashbacks, plinths, end panels and final adjustments.

Who handles what

A kitchen fit is a team job. The carpenter or kitchen fitter installs the units, worktops (laminate and timber), doors, panels and plinths. A plumber handles water supplies, wastes, the sink and any dishwasher or washing machine connections. An electrician installs new circuits and sockets, the hob and oven supply, extraction and lighting; much of this is notifiable work under building regulations and should be certified. A plasterer makes good the walls after first fix, and a tiler does splashbacks and floors where needed.

Any gas work, such as a gas hob, must be done by a Gas Safe registered engineer. When one contractor coordinates all of these, you avoid gaps such as the electrician arriving before the plasterer has finished.

Budgeting for the installation

When comparing prices, separate the cost of the kitchen itself (units, worktops, appliances, sink and taps) from the cost of installing it. Installation quotes vary a lot depending on what is included: strip out and waste removal, plumbing, electrics, plastering, tiling, flooring and decoration are sometimes included and sometimes not.

Ask for an itemised quote so you can see exactly which trades and materials are covered, and keep a contingency for things like rotten floorboards, old wiring that needs replacing or uneven walls that only show up once the old units come out.

How long does it take?

A like-for-like replacement where nothing moves can take around one to two weeks of work on site. A kitchen with new plumbing and electrics, plastering and a layout change commonly takes longer, often three to four weeks, and the gap waiting for stone worktops can add time.

You will usually be without a working kitchen for most of that period, so plan a temporary set-up with a kettle, microwave and fridge.

Common problems and how to avoid them

  • Uneven walls and floors: older houses are rarely square. Good fitters scribe and pack units properly rather than leaving gaps.
  • Missing parts: check deliveries the day they arrive so missing panels or hinges are reordered before the fitter needs them.
  • Appliances not matching the plan: confirm exact model sizes and ventilation needs before the units are fitted.
  • Poor extraction: an extractor needs a proper duct route to the outside to work well.
  • Not enough sockets: think about where small appliances and chargers will live.
  • Late decisions on worktops and tiles, which hold up the whole job.

Frequently asked questions

Can you fit a kitchen I have bought myself?
Yes, we can install kitchens supplied by you. We recommend we see the plan before ordering so any issues with the room are spotted early.
Do I need building regulations approval for a new kitchen?
Usually not for the units themselves, but new electrical circuits, some drainage changes and removing walls do need to meet building regulations.

Talk to us about your project

Book your free, no-obligation initial site consultation. We cover Bognor Regis, Littlehampton, Chichester, Worthing, East Preston, Findon, Rustington.

07346 814853

Unit B, Lelliot and Co, Ash Grove / Heath Place, Bognor Regis PO22 9SL · Monday to Friday, 8am – 7pm