Snagging is the process of identifying incomplete details, minor defects and items that do not match the agreed specification. A door that catches, a missed sealant joint or a damaged tile may all belong on a snagging list. Something more serious, such as a leak or unsafe electrical fitting, needs prompt investigation rather than being left for a routine finishing visit.

Handover is broader than snagging. It includes understanding the new building services, receiving the relevant certificates and agreeing how outstanding work will be finished. For homeowners in West Sussex, a useful handover combines a careful walk-through with a clear document pack, named contacts and a realistic plan for checking how the work settles during use.

Home refurbishment by FirstR8 Builds, West Sussex

Agree the handover process before the final week

Check the contract for its definition of completion, the process for identifying defects and the conditions for final payment. Practical completion, where that term is used, does not necessarily mean that every tiny blemish has disappeared. However, a house should not be treated as ready simply because the agreed moving date has arrived when essential safety or usability issues remain.

Arrange a joint inspection with the builder while there is still time to organise return visits. If a designer or contract administrator is appointed, establish who prepares the formal list and assesses completion. An independent surveyor can be useful for complex work or disputed defects, but an ordinary snagging inspection is not a substitute for structural design checks or required inspections.

Create one dated list with room references, photographs and a clear description of each issue. State the agreed action, responsible person and target date. Distinguish damage from unfinished work and possible technical defects. Avoid several competing lists spread across messages, because both parties need to know which record is current.

Choose the right moment for each inspection

Checks should happen throughout the project, not just after decoration. Concealed work such as insulation, waterproofing details and service routes may be impossible to assess once covered. Ask what inspection records and photographs will be kept, but remember that photographs alone do not demonstrate compliance. Building control inspections must be arranged at the relevant stages.

For a finishing inspection, allow plaster and other wet materials to dry sufficiently for the intended finish. There is no reliable universal drying period: thickness, ventilation, temperature and weather all matter. Decoration applied too early can hide moisture temporarily and then fail. Follow the plaster, paint and flooring manufacturers’ conditions rather than working backwards from a party or furniture delivery.

Inspect in good daylight and with the installed lighting switched on. Test doors, drawers and fittings through normal use without forcing them. Do not walk on unfinished roofs, remove electrical covers or enter unsafe loft areas. If equipment cannot yet be commissioned, record that explicitly rather than marking the item complete.

Check living rooms, bedrooms, halls and joinery

Work methodically from the entrance around each room, then inspect the ceiling, floor and fittings. Compare what has been installed with the agreed drawings, schedules and samples. Existing surfaces may have agreed limitations, so distinguish new damage from imperfections that were documented before work began. A photographic condition record is useful here.

Look at decorated surfaces under normal viewing conditions and discuss concerns against the agreed standard. Freshly plastered walls are not automatically perfectly flat, and aggressive inspection with a torch pressed against a wall can exaggerate minor texture. Conversely, obvious unfinished patches should not be dismissed merely because decoration is subjective.

  • Doors and windows: check smooth operation, latches, handles, locks, seals and supplied keys.
  • Skirting and architrave: look for loose sections, damaged edges, unfinished joints and missed decoration.
  • Floors and stairs: check movement, damaged boards, trip edges, secure handrails and agreed transitions.
  • Storage: operate drawers and wardrobe doors, check shelves and inspect accessible internal finishes.
  • Lighting and sockets: confirm agreed locations and operation without opening or dismantling fittings.
  • Alarms: request a demonstration of the installed smoke, heat and carbon monoxide alarms as applicable.

Test kitchens, bathrooms and external details

Operate kitchen doors and drawers with adjacent appliances in place. Check worktop joints, visible cut edges and the fit around sinks. Run taps, fill and drain sinks, and look inside accessible cupboards for drips. A quick test cannot reveal every concealed problem, so report any later staining or musty smell promptly.

In bathrooms, check that sanitary fittings are secure and accessible outlets work as intended. Look at tile edges, grout, sealant and shower screens, then observe drainage during ordinary use. Waterproofing behind tiles cannot be verified just by looking at the finished surface. Ask for installation information and relevant photographs where a tanking system has been used.

Outside, inspect safely from ground level. Check thresholds, paths, visible gutters and drainage routes, particularly where levels have changed. Coastal wind-driven rain can expose weaknesses that a dry-weather inspection misses. Record any need for a follow-up after rainfall, but do not assume every damp mark is condensation or that every leak can wait for the next scheduled visit.

  • Check appliance documentation, ventilation openings and access to isolation points.
  • Ask for a demonstration of heating controls, extract fans and any ventilation boost settings.
  • Confirm external doors close and lock properly and rainwater outlets are not blocked with building debris.
  • Record remaining protective films, temporary fittings and waste that still need removal.

Understand the certificates you should receive

For work requiring building regulations approval, obtain the completion certificate from the building control body once the relevant process is complete. This is separate from planning permission and from a builder’s invoice. It is important evidence for your records, but it is not a comprehensive workmanship warranty or confirmation that every surface has been inspected.

For a new electrical installation or relevant additions and alterations, ask for the appropriate electrical certification. An Electrical Installation Certificate, often shortened to EIC, records relevant installation and test information; some smaller works use a Minor Electrical Installation Works Certificate instead. Where electrical work is notifiable under Part P, the building regulations compliance documentation is a separate consideration.

Gas work should be carried out by a suitably qualified Gas Safe registered engineer. Ask for the commissioning and service records relevant to the appliance and the building regulations compliance certificate where notification is required. A landlord gas safety record is a different document; it is not the universal handover certificate for every owner-occupied installation.

For applicable replacement windows and doors, a registered installer may self-certify compliance through schemes such as FENSA or CERTASS. Alternatively, compliance may be dealt with through building control. Do not demand a FENSA certificate for every window in an extension: establish which route applies to your particular work and keep the corresponding evidence.

Collect warranties and operating information

Ask for manufacturers’ warranties, product details, serial numbers and purchase or installation dates where relevant. Check whether registration is required and who must complete it. A manufacturer’s warranty usually has conditions and exclusions; it should not be confused with an unrestricted guarantee covering the entire project or with your statutory consumer rights.

Operations and maintenance information, often called O&M information, explains how to use and care for the finished work. For a domestic project this can be a straightforward organised folder rather than a large manual. Include heating settings, ventilation instructions, cleaning restrictions and maintenance intervals for specialist finishes, roofing products or external joinery.

Have the builder show you stopcocks, electrical isolation, heating pressure controls and accessible service valves. Keep labelled photographs of service routes before they disappear behind finishes, where available. Store digital copies securely with drawings, approvals and the final agreed specification so information survives a lost paper folder or a future change of owner.

Handle retention and outstanding payments fairly

A retention is an agreed sum held back under the contract, commonly associated with completion and a later defects period. It is not automatic, and there is no universal domestic percentage or release date. If you want retention, agree the mechanism before signing, including when each part becomes payable and how outstanding defects will be assessed.

Do not invent a retention after work has finished or assume that withholding the whole final payment is always justified by a minor defect. Follow the payment and notice provisions in the agreement, and seek advice if liability or the amount is disputed. Keep a clear record of money already paid and any agreed deductions.

Agree reasonable access for remedial work and confirm when each item has been checked. If a repair is unsatisfactory, explain why with evidence rather than simply reopening the entire list. For safety concerns, active leaks or suspected serious structural defects, seek appropriate professional assistance promptly instead of relying on the routine defects timetable.

Monitor drying-out cracks without ignoring warning signs

New plaster, timber and other materials can change as construction moisture leaves and heating patterns settle. Fine cracks at junctions, along plasterboard joints or where different materials meet can be part of normal drying and movement. Their significance depends on the pattern, history and associated symptoms, not simply whether they appeared in the first year.

Keep rooms reasonably ventilated and heat them steadily in line with the builder’s and manufacturers’ guidance. Do not block ventilation openings to make a new room warmer, and avoid aggressive forced drying without advice. Record cracks with dated photographs and a scale, then discuss the appropriate time for any cosmetic making good.

Cracks that widen, repeatedly reopen, appear stepped through masonry or accompany sticking openings, bulging or noticeable movement need assessment. There is no single width that makes every crack harmless or dangerous. Report changes and obtain a structural engineer’s advice where movement is suspected. Handover should establish who receives these reports and how urgent issues are escalated.

Frequently asked questions

Should I snag before moving furniture back in?
Yes, where practical. Clear access makes floors, joinery and decoration easier to inspect and helps distinguish construction damage from later moving damage. Some checks still need normal occupation, rainfall or heating use, so plan a follow-up.
Is a completion certificate the same as a warranty?
No. A building control completion certificate concerns the building regulations process. It does not provide an all-purpose guarantee of workmanship, replace product warranties or remove the need to inspect and report defects.
Do all electrical jobs need an EIC?
No. The appropriate certificate depends on the work. New installations and certain alterations require an EIC; some minor changes use a Minor Electrical Installation Works Certificate. Notifiable work also needs the applicable building regulations compliance evidence.
Can I keep a retention if none was agreed?
Do not assume so. Retention should be a contractual arrangement. If there are defects or a payment dispute, follow the contract and obtain advice about your rights and obligations before withholding money.
Are hairline cracks always normal after renovation?
No. Some fine cracks reflect drying or seasonal material movement, but pattern and progression matter. Photograph changes and seek advice if cracking grows, recurs or appears with distortion, sticking doors or other signs of movement.

Talk to us about your project

Book your free, no-obligation initial site consultation. We cover Bognor Regis, Littlehampton, Chichester, Worthing, East Preston, Findon, Rustington.

07346 814853

Unit B, Lelliot and Co, Ash Grove / Heath Place, Bognor Regis PO22 9SL · Monday to Friday, 8am – 7pm