The Building Safety Act 2022 is best known for its rules on high-rise residential buildings, but some of the changes that followed it also apply to ordinary home projects such as extensions, loft conversions and structural alterations. The biggest change for homeowners is that everyone involved in building work, including the person paying for it, now has a named role and responsibilities under the Building Regulations.
This guide explains those roles in plain terms, how they affect a typical house project and what you should expect from your designer and builder. It is a general overview, not legal advice. FirstR8 Builds offers a free, no-obligation initial site consultation, where these points can be discussed for your project.

In short
For a typical house project you are the client, and you are expected to appoint competent people, allow enough time and resources for the work to comply, and cooperate with them. Where more than one contractor is involved, there should be a principal designer and a principal contractor. Building control approval, inspections and completion certificates still apply as before.
What changed and when
The Act set up the Building Safety Regulator and reformed building control. From October 2023, new dutyholder and competence requirements were added to the Building Regulations in England, and private building control professionals now have to be registered. From April 2024, registered building control approvers replaced the older approved inspector system.
For buildings that are not high-rise, which includes almost every house, the approval process is broadly familiar: you still choose either the local authority or a registered building control approver, submit plans or a building notice where allowed, and have the work inspected. What is new is the clearer allocation of responsibility.
The dutyholder roles on a house project
The Building Regulations now name several roles. On a domestic project they usually look like this:
- Client: the person or people the work is being done for, usually the homeowner.
- Designer: anyone who prepares or changes the design, such as an architect, architectural technician or structural engineer, and also a builder who makes design decisions on site.
- Contractor: anyone carrying out or managing the building work.
- Principal designer: the designer in control of the design phase where more than one contractor is involved.
- Principal contractor: the contractor in control of the building phase where more than one contractor is involved.
Your duties as a domestic client
As a domestic client, your main responsibilities are to make suitable arrangements for the work to comply with the regulations, to appoint people who have the right skills, knowledge, experience and behaviours for the job, and to cooperate and share relevant information, such as drawings, surveys and any known problems with the house.
On many domestic projects, if you do not appoint a principal designer and principal contractor in writing, the regulations treat the designer in control of the design and the contractor in control of the build as having those roles. This is one reason a clear written agreement with your builder and designer is useful: everyone knows who is responsible for what.
Practically, it means checking that the people you hire are competent for the type of work, for example by asking about similar work they have done and seeing photos, rather than hiring on price alone.
What it means for designers and builders
Designers must make sure their designs comply with the Building Regulations so far as they can, and builders must plan, manage and monitor the work so that it complies. Both must only take on work they are competent to do and must tell the client about their duties.
Where a builder changes the design on site, for example altering a beam detail or moving a window, they take on design responsibility for that change. Changes should be recorded and, where they affect compliance, agreed with building control.
Building control under the new system
Your application still goes either to the local authority building control team or to a registered building control approver. Inspectors check key stages such as foundations, drainage, structure and insulation before they are covered up, then issue a completion or final certificate when satisfied.
Keep every document: the approval, inspection records, structural calculations, electrical and gas certificates and the completion certificate. A future buyer's solicitor will ask for them, and missing paperwork is a common cause of delays in a sale. Our Building Regulations guide explains full plans and building notice routes.
Does it apply to smaller jobs?
The dutyholder rules apply to building work that falls under the Building Regulations, such as extensions, loft and garage conversions, removing load-bearing walls and some renovation work. Work that does not need building control approval, such as fitting a new kitchen layout without structural, drainage or electrical notifiable changes, or straightforward joinery like skirting and internal doors, is generally outside the approval process. If in doubt, ask building control before starting.
Mistakes to avoid
- Assuming the Act only affects tower blocks and ignoring your role as client.
- Splitting a project between several trades with nobody clearly in charge of design or the build.
- Making design changes on site without telling the designer or building control.
- Not giving the builder existing surveys, drawings or known defects.
- Losing the completion certificate and other records at the end of the job.
Frequently asked questions
- Does the Building Safety Act affect my house extension?
- Yes, in part. The high-rise regime does not apply to houses, but the dutyholder and competence rules added to the Building Regulations apply to building work such as extensions and loft conversions.
- Am I a client under the Building Regulations?
- If the work is being done for you, yes. Your duties are mainly to appoint competent people, allow enough time and resources and cooperate with your designer and builder.
- Do I have to appoint a principal designer for a house project?
- Where more than one contractor is involved, there should be a principal designer and principal contractor. On many domestic jobs, if you do not appoint them in writing, the designer and contractor in control take on those roles.
- Can I still use a private building inspector?
- Yes, but they must now be a registered building control approver. You can choose them or your local authority building control.
- Has building control approval changed for houses?
- The process is broadly similar, with plans or a building notice, inspections and a completion certificate. The main change is clearer responsibility for compliance.